Multi-objective optimisation of assembly line balancing type-e problem with resource constraints

Assembly Line Balancing (ALB) is an attempt to assign tasks to various workstations along a line so that the precedence relations are satisfied and some performance measures are optimised. In this research, a few tasks that use similar resources will be assigned in the same workstation by ensuring...

Full description

Bibliographic Details
Main Author: Masitah, Jusop
Format: Thesis
Language:English
English
English
Published: 2016
Subjects:
Online Access:http://umpir.ump.edu.my/id/eprint/18121/
http://umpir.ump.edu.my/id/eprint/18121/
http://umpir.ump.edu.my/id/eprint/18121/1/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Table%20of%20contents.pdf
http://umpir.ump.edu.my/id/eprint/18121/7/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Abstract.pdf
http://umpir.ump.edu.my/id/eprint/18121/8/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-References.pdf
id ump-18121
recordtype eprints
repository_type Digital Repository
institution_category Local University
institution Universiti Malaysia Pahang
building UMP Institutional Repository
collection Online Access
language English
English
English
topic TJ Mechanical engineering and machinery
spellingShingle TJ Mechanical engineering and machinery
Masitah, Jusop
Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
description Assembly Line Balancing (ALB) is an attempt to assign tasks to various workstations along a line so that the precedence relations are satisfied and some performance measures are optimised. In this research, a few tasks that use similar resources will be assigned in the same workstation by ensuring that it does not violate the precedence constraint and that the total processing time in each workstation is approximately the same and does not exceed the cycle time. Assumption by previous researches that any assembly task can be performed in any workstation encourages the author to focus on the resource usage in ALB. Limited number of resources in the industry also becomes a vital influencer to consider this constraint in ALB. Apart from that, Elitist Non-Dominated Sorting Genetic Algorithm (NSGA-II) has not yet been implemented by previous researcher in the optimisation of Assembly Line Balancing Type-E (ALB-E) itself with resource constraints. The aim of this research is to establish a mathematical model for ALB-E with resource constraints (ALBE-RC). This research is proposed to be conducted in three main phases. After conducting literature review, the modelling phase will be performed. In the second phase of this research, an algorithm will be developed to optimise the problem. Later, the optimisation algorithm will be tested and verified using test problems from literature. The third phase of this research is, an industrial case study will be conducted for the purpose to validate the mathematical model and the optimisation algorithm. This research gap was identified when none of the previous research considered machine, tool, and worker constraint in ALB-E. In this research, a Genetic-based Algorithm was used as an optimisation approach. The Elitist Non-Dominated Sorting Genetic Algorithm (NSGA-II) has been proposed to optimise ALBE-RC. The optimisation result indicated that the NSGA-II algorithm has better performance in finding non dominated solution due to small error ratio and small generational distance as compared to other algorithms like Multi-Objective Genetic Algorithm (MOGA) and Hybrid Genetic Algorithm (HGA). The results indicate that NSGA-II has the ability to explore the search space and has better accuracy of solution towards Pareto-optimal front. The validation phase from the industrial case study concluded that the proposed methodology and algorithm can be implemented in industries. The cycle time of existing layout had been extensively decreased from 16.1 seconds to 13.1 seconds after the optimisation. The number of workstations was decreased after the optimisation from 17 workstations to nine (9) workstations. Meanwhile, the number of resources used were reduced from 43 resources to 40 resources. Apart from that, the percentage of line efficiency improved from 33.8% to 78.4%. These results indicated that the developed methodology and the proposed algorithm can reduce the utilisation of resources, workstations and cycle time. In fact, the aforementioned approach also can increase the efficiency of assembly process as well as enhance the industrial productivity.
format Thesis
author Masitah, Jusop
author_facet Masitah, Jusop
author_sort Masitah, Jusop
title Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
title_short Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
title_full Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
title_fullStr Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
title_full_unstemmed Multi-objective optimisation of assembly line balancing type-e problem with resource constraints
title_sort multi-objective optimisation of assembly line balancing type-e problem with resource constraints
publishDate 2016
url http://umpir.ump.edu.my/id/eprint/18121/
http://umpir.ump.edu.my/id/eprint/18121/
http://umpir.ump.edu.my/id/eprint/18121/1/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Table%20of%20contents.pdf
http://umpir.ump.edu.my/id/eprint/18121/7/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Abstract.pdf
http://umpir.ump.edu.my/id/eprint/18121/8/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-References.pdf
first_indexed 2023-09-18T22:25:28Z
last_indexed 2023-09-18T22:25:28Z
_version_ 1777415937006239744
spelling ump-181212017-07-11T03:34:51Z http://umpir.ump.edu.my/id/eprint/18121/ Multi-objective optimisation of assembly line balancing type-e problem with resource constraints Masitah, Jusop TJ Mechanical engineering and machinery Assembly Line Balancing (ALB) is an attempt to assign tasks to various workstations along a line so that the precedence relations are satisfied and some performance measures are optimised. In this research, a few tasks that use similar resources will be assigned in the same workstation by ensuring that it does not violate the precedence constraint and that the total processing time in each workstation is approximately the same and does not exceed the cycle time. Assumption by previous researches that any assembly task can be performed in any workstation encourages the author to focus on the resource usage in ALB. Limited number of resources in the industry also becomes a vital influencer to consider this constraint in ALB. Apart from that, Elitist Non-Dominated Sorting Genetic Algorithm (NSGA-II) has not yet been implemented by previous researcher in the optimisation of Assembly Line Balancing Type-E (ALB-E) itself with resource constraints. The aim of this research is to establish a mathematical model for ALB-E with resource constraints (ALBE-RC). This research is proposed to be conducted in three main phases. After conducting literature review, the modelling phase will be performed. In the second phase of this research, an algorithm will be developed to optimise the problem. Later, the optimisation algorithm will be tested and verified using test problems from literature. The third phase of this research is, an industrial case study will be conducted for the purpose to validate the mathematical model and the optimisation algorithm. This research gap was identified when none of the previous research considered machine, tool, and worker constraint in ALB-E. In this research, a Genetic-based Algorithm was used as an optimisation approach. The Elitist Non-Dominated Sorting Genetic Algorithm (NSGA-II) has been proposed to optimise ALBE-RC. The optimisation result indicated that the NSGA-II algorithm has better performance in finding non dominated solution due to small error ratio and small generational distance as compared to other algorithms like Multi-Objective Genetic Algorithm (MOGA) and Hybrid Genetic Algorithm (HGA). The results indicate that NSGA-II has the ability to explore the search space and has better accuracy of solution towards Pareto-optimal front. The validation phase from the industrial case study concluded that the proposed methodology and algorithm can be implemented in industries. The cycle time of existing layout had been extensively decreased from 16.1 seconds to 13.1 seconds after the optimisation. The number of workstations was decreased after the optimisation from 17 workstations to nine (9) workstations. Meanwhile, the number of resources used were reduced from 43 resources to 40 resources. Apart from that, the percentage of line efficiency improved from 33.8% to 78.4%. These results indicated that the developed methodology and the proposed algorithm can reduce the utilisation of resources, workstations and cycle time. In fact, the aforementioned approach also can increase the efficiency of assembly process as well as enhance the industrial productivity. 2016-11 Thesis NonPeerReviewed application/pdf en http://umpir.ump.edu.my/id/eprint/18121/1/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Table%20of%20contents.pdf application/pdf en http://umpir.ump.edu.my/id/eprint/18121/7/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-Abstract.pdf application/pdf en http://umpir.ump.edu.my/id/eprint/18121/8/Multi-objective%20optimisation%20of%20assembly%20line%20balancing%20type-e%20problem%20with%20resource%20constraints-References.pdf Masitah, Jusop (2016) Multi-objective optimisation of assembly line balancing type-e problem with resource constraints. Masters thesis, Universiti Malaysia Pahang. http://iportal.ump.edu.my/lib/item?id=chamo:99925&theme=UMP2